Capital Improvement Program

14 active projects across a $82.2M program

Permit headroom6.95 / 12.50 MGD — 44.4% headroom
NPDES CA0038539

Key insights — Apr 26

Derived from this page’s source data
Delivery

$31.8M spent of $68.4M (46%)

$17.2M further committed across 14 active projects; 76.0% delivery against plan.

Schedule

8 projects behind forecast finish

Largest slip: Hilltop Trunk Sewer Rehabilitation at 34 days.

Risk

3 projects rated high risk

Risk rating is derived from schedule variance and forecast-at-completion against current budget.

Process

Change orders averaging 26.4 days against a 21-day target

17 open workflow items are past their cycle-time target.

Program budget
$82.2M
current, including approved changes
Expended to date
$36.7M
44.7% of budget
Committed
$55.2M
contracts and encumbrances
Change orders
$2.8M
3.4% of original budget
Projects behind schedule
8
of 14 active

Project schedule — planned vs. forecast finish

schedule variance in days
CIP-24-101North Richmond Living Levee & Sustainability Project
43%-18d
CIP-23-090Clean & Green Energy Project — Microgrid and Solar
72%-5d
CIP-24-108Hilltop Trunk Sewer Rehabilitation
39%+34d
CIP-25-112Lift Station 7 Rehabilitation
34%+19d
CIP-25-118Headworks Screening Improvements
18%+26d
CIP-25-114Annual Sewer Lateral & Main Replacement, Phase 12
73%+23d
CIP-26-121SCADA System Upgrade
11%-14d
CIP-24-106Secondary Clarifier No. 3 Rehabilitation
47%-10d
CIP-25-116Force Main Condition Assessment & Repair
22%+31d
CIP-26-123Administration Building Seismic Retrofit
6%-38d
CIP-24-104Recycled Water Pump Station Expansion
44%-43d
CIP-25-119Lift Stations 3 & 11 Electrical Upgrades
18%+1d
CIP-23-088Digester Gas Handling Improvements
94%+23d
CIP-24-110Collection System Master Plan Update
98%+23d

Program cash flow

FY25-26 · planned vs. actual

Project portfolio

budget, cost and schedule by project
ProjectNameProgramPhasePMOriginalChangesCurrentExpendedForecast% completeSched. var.FundingRisk
CIP-24-101North Richmond Living Levee & Sustainability ProjectResiliency & SustainabilityDesignM. Savannah$14.8M$0.1M$14.9M$5.9M$15.8M
43%
-18 dFederal AppropriationLow
CIP-23-090Clean & Green Energy Project — Microgrid and SolarResiliency & SustainabilityConstructionR. Delacroix$12.4M$0.6M$13.0M$8.9M$13.7M
72%
-5 dSRF LoanLow
CIP-24-108Hilltop Trunk Sewer RehabilitationCollection System RehabilitationConstructionT. Okonkwo$8.9M$0.3M$9.2M$3.7M$9.6M
39%
+34 dRate RevenueHigh
CIP-25-112Lift Station 7 RehabilitationLift Station ImprovementsDesignA. Villanueva$4.6M$0.3M$4.9M$1.6M$5.2M
34%
+19 dRate RevenueMedium
CIP-25-118Headworks Screening ImprovementsTreatment Plant UpgradesBid & AwardS. Hartley$5.3M$0.4M$5.6M$1.0M$5.6M
18%
+26 dSRF LoanHigh
CIP-25-114Annual Sewer Lateral & Main Replacement, Phase 12Collection System RehabilitationConstructionM. Savannah$6.1M$0.3M$6.4M$4.5M$6.3M
73%
+23 dRate RevenueMedium
CIP-26-121SCADA System UpgradeFacilities & TechnologyPlanningR. Delacroix$3.4M$0.1M$3.5M$0.4M$3.7M
11%
-14 dRate RevenueLow
CIP-24-106Secondary Clarifier No. 3 RehabilitationTreatment Plant UpgradesConstructionT. Okonkwo$5.0M$0.3M$5.2M$2.3M$5.2M
47%
-10 dRate RevenueLow
CIP-25-116Force Main Condition Assessment & RepairCollection System RehabilitationDesignA. Villanueva$2.8M$0.1M$2.8M$0.5M$2.8M
22%
+31 dGrantHigh
CIP-26-123Administration Building Seismic RetrofitFacilities & TechnologyPlanningS. Hartley$3.1M$0.1M$3.2M$0.2M$3.2M
6%
-38 dRate RevenueLow
CIP-24-104Recycled Water Pump Station ExpansionResiliency & SustainabilityConstructionM. Savannah$5.8M$0.1M$5.9M$2.3M$6.3M
44%
-43 dGrantLow
CIP-25-119Lift Stations 3 & 11 Electrical UpgradesLift Station ImprovementsBid & AwardR. Delacroix$2.3M$0.0M$2.3M$0.4M$2.3M
18%
+1 dRate RevenueMedium
CIP-23-088Digester Gas Handling ImprovementsTreatment Plant UpgradesCloseoutT. Okonkwo$3.7M$0.2M$3.9M$3.9M$4.2M
94%
+23 dSRF LoanMedium
CIP-24-110Collection System Master Plan UpdateCollection System RehabilitationCloseoutA. Villanueva$1.4M$0.1M$1.4M$1.2M$1.5M
98%
+23 dConnection FeesMedium

Process cycle times

e-Builder workflow performance
ProcessAvg daysTargetOpenOver target
Change Orders26.42173
RFIs9.810224
Submittals14.214419
Pay Applications18.62191

A $184,500 change order on the Hilltop Trunk Sewer Rehabilitation has been pending 34 days — the single largest schedule risk in the program this period.

View linked Monday.com items →

Ten-year capital plan by program

$ by fiscal year

Projects by phase

Planning2
$6.7M programmed
  • SCADA System Upgrade
  • Administration Building Seismic Retrofit
Design3
$22.6M programmed
  • North Richmond Living Levee & Sustainability Project
  • Lift Station 7 Rehabilitation
  • Force Main Condition Assessment & Repair
Bid & Award2
$7.9M programmed
  • Headworks Screening Improvements
  • Lift Stations 3 & 11 Electrical Upgrades
Construction5
$39.8M programmed
  • Clean & Green Energy Project — Microgrid and Solar
  • Hilltop Trunk Sewer Rehabilitation
  • Annual Sewer Lateral & Main Replacement, Phase 12
  • Secondary Clarifier No. 3 Rehabilitation
  • Recycled Water Pump Station Expansion
Closeout2
$5.3M programmed
  • Digester Gas Handling Improvements
  • Collection System Master Plan Update

Total programmed value 82,230,023 USD across 14 projects and 5 programs.